POWERHOUSE PLACE

Reinvigorating Mildura’s historic powerhouse and riverfront.

INTRODUCTION

Place is never neutral. This place is for the people.

Why Us?

MRCC had secured state government funding to reinvigorate their historic powerhouse and reconnect Mildura’s CBD to her river - the Might Murray. Council’s priorities were:

  1. sensitive and sympathetic revitalisation of the historic powerhouse,

  2. activation to ensure that there was always something to see or do at Powerhouse Place

  3. operational effectiveness so that Council could afford to own and operate this asset.

Our way of aligning strategy, culture and place gave Council confidence that we would champion solutions that met real community need, that were flexible, low cost and viable. Our experience revitalising historic buildings and driving community wellbeing and connection through low cost activations sealed the deal.

HOW DID WE HELP?

Council had already completed community engagement and the masterplan before appointing us, so we started by fleshing out the size and layouts of buildings that they had decided on about a year earlier. When the community and Councillors understood what this would look like and how it would change this part of the riverfront, they realised it wasn’t what they actually wanted. We cut our Christmas holidays short and went back to the beginning: helping the community, stakeholders and Councillors articulate a shared vision for this place. We did this through workshops, surveys and by presenting detailed case studies to unpack what might work.

In the end we:

  • Developed a new masterplan for the precinct that had community and Council support

  • Created infinitely flexible, low-cost spaces to support a community-led revitalisation

  • Transformed the precinct

  • Drove increased investment in Mildura

MIL_TR1.jpg

PROBLEMS

What problems did we solve and how?

BEHIND THE SCENES

A glimpse of how we made it happen:

AUDIENCE

So it's a place for the people. But which people?

Every stakeholder in Powerhouse Place - community, Council, businesses - were clear that this place needed to be safe and accessible for everyone. We knew we had to actively challenge the status quo - the social model of disability and the prioritisation of white settler history.  The powerhouse was undeniably part of a colonial project - extracting natural resources and sustaining settlement. Creating Powerhouse Place was a chance to start thinking about restorative placemaking - working with Country through biogenic materials, increasing tree canopy, reintroducting endemic species and creating a space for truthtelling and deep listening. Yennaga Jaanji - come listen.  

To create a place where all bodies and abilities can thrive we went above and beyond the requirements of the building code and made sure that:

  • Toilet and changing amenities are clearly visible, highly supportive and distributed around Powerhouse Place so that they are always a short distance away 

  • All paths of travel are accessible, well lit and inviting

  • All gender facilities are provided throughout

The landmark tenancy in the powerhouse is occupied by social enterprise the Chistie Centre, who demonstrate their generosity, capacity and creativity through their cafe, store and ongoing use of Powerhouse Place.

  • “The design manages to create a fresh new look along our riverfront while still respecting the history of the precinct.”

    Councillor Liam Wood,
    Former Mayor
    Mildura

  • In a time of limited resources, Powerhouse Place serves as an exemplar of a different way of working, one where success is defined by the degree of ownership and occupation of a site by a community. It is restrained, yet generous and demonstrates how minimal architectural intervention is necessary to create a sense of place.

    Victorian Architecture Awards
    Regional Prize
    Jury Citation

SUMMARY

The first public hemp masonry buildings in Australia

ANY SURPRISES?

It’s not often that viruses change architecture but COVID really did change what Mildurans valued about their riverfront, remoteness and community.  This change of heart meant the community withdrew its support for a masterplan that emerged from extensive community consultation (by others) and had been endorsed only 12 months earlier. This meant that - with the stimulus funding clock ticking - we had to go back to the beginning and win the social license to create Powerhouse Place (see Problem #1). 

IS IT SUSTAINABLE?

The three new buildings at powerhouse place are the first public hemp masonry buildings in Australia. We pioneered this locally grown, carbon sequestering, super insulating construction material because we believe it is the future of regenerative construction. 

Powerhouse Place sets the precedent for public hemp construction and is being used in advocacy efforts to support hemp construction across Australia. Powerhouse place is also gas free, fully electric and powered by a 40W PV array system with 30kW inverter and 5kW battery.  The site encourages and supports active transport by providing shade, amenity, bike parking and connectivity to other trails both along the riverfront and to the CBD.  Tree canopy coverage and planting has been increased as part of the project. 

Powerhouse Place has been recognised for leadership in Sustainable Architecture with awards at both state and national level.

PROJECT DETAILS

CLIENT: MILDURA REGIONAL CITY COUNCIL

LOCATION: MILDURA, VICTORIA MILLEWA MALLEE COUNTRY

STATUS: COMPLETE

COMPLETED: OCTOBER 2023

VALUE: $10.32M

SIZE: 1,000M2

Services

Consultation + Engagement

Masterplan + Feasibility Study   

Urban Design

Architectural Services

Placemaking + Activation

Awards

Victorian Architecture Awards, 2024:

Joseph Reed Award for Urban Design,

Allan and Beth Coldicutt Award for Sustainable Architecture

Regional Prize

Victorian Architecture Medal

National Architecture Awards, 2024:

Award for Urban Design

Award for Sustainable Architecture

Funding Streams

Australian Government: $2.9M

Murray-Darling Basin Economic Development Program Round 3: $1M

Local Roads and Community Infrastructure Funding: $1.0M

Victorian Government: $5.985M

Infrastructure Stimulus Fund: $5M

Regional Infrastructure Fund: $500,000

Sustainable Infrastructure Fund: $196,000

Changing Places Funding: $110,000

Women in Public Art: $109,000

Creative Neighbourhoods Program: $70,000

Mildura Rural City Council: $1.447 million